2010 : Additions & Renovations

Allen ES
Library Renovation
94% Complete
Cost: $583,424*
Construction: 04/2012 to 08/2012

Architect: Shawn Kaarlsen & Associates
Contractor: D.L. Bandy
Client Contact: Marilyn Sevedge
Clark HS
Library Renovation
94% Complete
Cost: $254,400*
Construction: 04/2012 to 08/2012

Architect: Shawn Kaarlsen & Associates
Contractor: D.L. Bandy
Client Contact: Marilyn Sevedge
Glass ES
Cafeteria Renovation
23% Complete
Cost: $1,255,917*
Construction: 05/2012 to 12/2012

Architect: O'Connell Robertson & Assoc
Contractor: Swinerton Builders, Inc.
Client Contact: Tom Curiel
Helotes ES
Library Renovation
94% Complete
Cost: $583,424*
Construction: 04/2012 to 08/2012

Architect: Shawn Kaarlsen & Associates
Contractor: D.L. Bandy
Client Contact: Marilyn Sevedge
Jay HS
Cafeteria Renovation
97% Complete
Cost: $1,802,455*
Construction: 03/2012 to 08/2012

Architect: Garza Architects
Client Contact: Tom Curiel
Jones MS
Science Labs
97% Complete
Cost: $5,771,332*
Construction: 06/2011 to 07/2012

Architect: Alamo Architects
Contractor: Joeris General Contractors
Client Contact: Jim Berg
Mary Hull ES
Cafeteria Renovation
23% Complete
Cost: $1,255,917*
Construction: 05/2012 to 12/2012

Architect: O'Connell Robertson & Assoc
Contractor: Swinerton Builders, Inc.
Client Contact: Tom Curiel
Michael ES
Classroom Addition
99% Complete
Cost: $1,850,000*
Construction: 05/2011 to 07/2012

Architect: Noonan Rittimann Architects
Contractor: WR Griggs Const.
Client Contact: Tom Curiel
Neff MS
Cafeteria Renovation
97% Complete
Cost: $2,046,030*
Construction: 03/2012 to 08/2012

Architect: Garza Architects
Contractor: Gamma Construction
Client Contact: Tom Curiel
O'Connor HS
Classroom Addition
99% Complete
Cost: $3,558,885*
Construction: 06/2011 to 07/2012

Architect: Marmon Mok
Contractor: Eaton Commercial
Client Contact: Jim Berg
Rayburn MS
Additions/Renovation
99% Complete
Cost: $9,425,126*
Construction: 04/2011 to 07/2012

Architect: Garza Bomberger Architects
Contractor: Joeris General Contractors
Client Contact: Jim Berg
Ross MS
Library Renovation
94% Complete
Cost: $1,383,936*
Construction: 04/2012 to 08/2012

Architect: Shawn Kaarlsen & Associates
Contractor: D.L. Bandy
Client Contact: Marilyn Sevedge
Stevenson MS
Science Lab
98% Complete
Cost: $5,483,017*
Construction: 06/2011 to 07/2012

Architect: Alamo Architects
Contractor: Joeris General Contractors
Client Contact: Jim Berg
Taft HS
HVAC Replacement
66% Complete
Cost: $18,670,039*
Construction: 06/2011 to 07/2013

Architect: Wallis Engineering
Contractor: Bartlett Cocke
Client Contact: Tom Curiel
Taft HS
Cafeteria Renovation
97% Complete
Cost: $1,023,015*
Construction: 03/2012 to 08/2012

Architect: Garza Architects
Contractor: Gamma Construction
Client Contact: Tom Cruiel
Villarreal ES
Library Renovation
94% Complete
Cost: $586,816*
Construction: 04/2012 to 08/2012

Architect: Shawn Kaarlsen & Associates
Contractor: D.L. Bandy
Client Contact: Marilyn Sevedge
Westwood Terrace
Cafeteria Renovation
23% Complete
Cost: $1,225,917*
Construction: 05/2012 to 12/2012

Architect: O'Connell Robertson & Assoc
Contractor: Swinerton Builders, Inc.
Client Contact: Tom Curiel
Zachry MS
Science Lab
98% Complete
Cost: $7,057,923*
Construction: 06/2011 to 07/2012

Architect: Alamo Architects
Contractor: Joeris
Client Contact: Jim Berg