Project Resources

Event
Date & Time
Location
Purpose
Meeting March 10, 2003
8:30 - Noon
C.O. Boardroom Needs assessment w/ instructional specialists
Presentation March 11, 2003
12:30 - 3:30
NLC Conf. Rm. Pearson Educational Technologies Presentation
Presentation March 13, 2003
12:30 - 3:30
NLC Conf. Rm. Campus Online
Presentation March 14, 2003
8:30 -11:30
NLC Conf. Rm. EdSoft
Presentation April 1 , 2003
8:30 -11:30
NLC Conf. Rm. Edmin
Presentation April 2 , 2003
1:30 - 4:30
NLC Conf. Rm. SchoolNet Presentation
Presentation April 3 , 2003
1:30 - 4:30
NLC Conf. Rm. LightSpan Presentation
Presentation April 7 , 2003
8:30 -11:30
NLC Conf. Rm. Edusoft
RFP Released

June 23, 2003 C.O. Purchasing Department Procurement Process
Deadline for RFP Questions from Vendors

July 7, 2003 by 5:00 p.m. C.O. Purchasing Department Procurement Process
Answers to RFP Questions Returned to Vendors

July 21, 2003 by 5:00 p.m. C.O. Purchasing Department Procurement Process
RFP Due Date

August 4, 2003 by 4:00 p.m. C.O. Purchasing Department Procurement Process
Preliminary Evaluation of Proposals Week of August 18, 2003 NLC Procurement Process
Vendor Presentations by Finalists
October-November, 2003 NLC Procurement Process
Final Evaluation and Scoring December, 2003 C.O. Procurement Process
Presentation to Academics Committee and Technology Committee of the Board February, 2004 C.O. Board Room Procurement Process
Final Vendor Selection and Announcement, Pending Board Approval
February, 2004 C.O. Board Room Procurement Process


Copyright © 2005. Northside Independent School District. All Rights Reserved.