Project Scheduling for Design and Construction

BOND PROGRAM 2001

YEAR 2 (2002-2003)

Project
Select Architect
Schematic Design
Design Development
Construction Documents
Proposals
Construction
Closeout
Carlos Coon ES Renovation
X
X
X
X
X
Sept. 2003 - Dec. 2004
X

Holmes HS Addition & Renovation

X
X
X
X
X
June 2003 - Dec. 2004
X
Taft HS Addition & Renovation
X
X
X
X
X
April 2003 - August 2004
X
Ott Elementary School No. 3 (Westcreek)
X
X
X
X
X
Jan. 2003 - July 2004
X
Luna Middle School (Westcreek)
X
X
X
X
X
January 2003 - July 2004
X
Project
Select Architect
Schematic Design
Design Development
Construction Documents
Proposals
Construction
Closeout
Northwest Crossing Elementary Addition & Renovation
X
X
X
X
X
June 2003 - August 2004
X
Hatchett Elementary School No. 5 (Westlakes)
X
X
X
X
X
February 2003 - Sept. 2004
X
Stevens High School
X
X
X
X
X
May 2003 - August 2005
X
New NISD Natatorium
X
X
X
X
X
Sept. 2004 - July 2006
X