BOND PROGRAM 2004
![]()
![]()
|
YEAR 1 (2004-2005) |
|
Project
|
Select Architect
|
Schematic Design
|
Design Development
|
Construction Documents
|
Proposals
|
Construction
|
Closeout
|
|
Fisher Elementary
|
X
|
X
|
X
|
X
|
X
|
January
2005- July 2006
|
X
|
|
Murnin Elementary |
X
|
X
|
X
|
X
|
X
|
March
2005- July 2006
|
X
|
|
Wanke Elementary
|
X
|
X
|
X
|
X
|
X
|
February
2005 - July 2006
|
X
|
|
Warren HS - Addition
|
X
|
X
|
X
|
X
|
X
|
May 2005
- June 2006
|
X
|
|
Lewis ES - Addition
|
X
|
X
|
X
|
X
|
X
|
April
2005 - June 2006
|
X
|
|
Stevenson MS - Addition
|
X
|
X
|
X
|
X
|
X
|
May 2004
- December 2006
|
X
|
|
Project
|
Select Architect
|
Schematic Design
|
Design Development
|
Construction Documents
|
Proposals
|
Construction
|
Closeout
|
|
Taft HS - Addition
|
X
|
X
|
X
|
X
|
X
|
May 2005
- December 2005
|
X
|
|
Glenn ES - Addition
|
X
|
X
|
X
|
X
|
X
|
August
2005 - April 2006
|
X
|
|
Timberwilde ES -
Renovations
|
X
|
X
|
X
|
X
|
X
|
May 2005
- August 2005
|
X
|
|
Reddix Center -
Addition
|
X
|
X
|
X
|
X
|
X
|
August
2005 - May 2006
|
X
|
|
Passmore ES - Addition
|
X
|
X
|
X
|
X
|
X
|
May 2004
- August 2005
|
X
|
|
Elementaries' - Gym A/C
|
X
|
X
|
X
|
X
|
X
|
April
2005 - November 2005
|
X
|
![]()
![]()
|