Project Scheduling for Design and Construction

BOND PROGRAM 2004

YEAR 2 (2005-2006)

Project
Select Architect
Schematic Design
Design Development
Construction Documents
Proposals
Construction
Closeout
Jefferson Middle School
X
X
X
X
X
December 2005- July 2007
X

Brandeis High School

X
X
X
X
X
March 2006- July 2008
X
Driggers Elementary
X
X
X
X
X
February 2006 - July 2007
X
Aue ES
X
X
X
X
X
March 2006 - July 2007
X
Sul Ross MS - Addition
X
X
X
X
X
April 2006 - August 2007
X
Leon Valley ES - Addition
X
X
X
X
X
January 2006 - March 2007
X
Project
Select Architect
Schematic Design
Design Development
Construction Documents
Proposals
Construction
Closeout
John Jay HS - Science Addition
X
X
X
X
X
April 2006 - August 2007
X
Hobby MS - Addition
X
X
X
X
X
May 2006 - August 2007
X
Anson Jones MS - Renovations
X
X
X
X
X
March 2006 - July 2007
X
Rudder MS - Addition
X
X
X
X
X
March 2006 - July 2007
X
Howsman ES - Renovation
X
X
X
X
X
February 2006 - August 2006
X
Pease MS - Kitchen
X
X
X
X
X
January 2007 - December 2007
X