BOND PROGRAM 2004
![]()
![]()
|
YEAR 3 (2006-2007) |
|
Project
|
Select Architect
|
Schematic Design
|
Design Development
|
Construction Documents
|
Proposals
|
Construction
|
Closeout
|
|
Potranco North MS
|
X
|
X
|
X
|
X
|
X
|
August
2006- July 2008
|
|
|
Carnahan Elementary |
X
|
X
|
X
|
X
|
X
|
January
2007- July 2008
|
|
|
Scarborough Elementary
|
X
|
X
|
X
|
X
|
X
|
May
2007 - July 2008
|
|
|
Forester Elementary
|
X
|
X
|
X
|
X
|
X
|
November
2006 - May 2008
|
|
|
Mary Hull ES - Addition
|
X
|
X
|
X
|
X
|
X
|
March
2007 - August 2008
|
|
|
Raba ES - Addition
|
X
|
X
|
X
|
X
|
X
|
December
2006 - December 2007
|
![]()
![]()
|
FACILITIES & OPERATIONS 5900 Evers Rd. San Antonio, TX. 78238 Tel.(210) 257-1200 Fax (210) 257-1212 |
Web Managers: Mario Castanares/Peter Cristan