BOND PROGRAM 2007
![]()
![]()
|
YEAR 2 (2008-2009) |
|
Project
|
Select Architect
|
Schematic Design
|
Design Development
|
Construction Documents
|
Proposals
|
Construction
|
Closeout
|
|
Alamo Ranch MS
|
X
|
X
|
X
|
August
2008 - June 2010
|
|||
|
Canterbury Farms ES |
X
|
August 2008 - July 2010
|
|||||
|
Laurel Mountain Ranch #1 ES
|
X
|
September
2008 - July 2010
|
|||||
|
Kallison Ranch #1 ES
|
X
|
January 2009
- July 2010
|
|||||
|
Warren HS - Addition
|
Sept. 2008 - July 2010
|
||||||
|
Pease MS - Addition
|
October 2008
- July 2010
|
||||||
|
Project
|
Select Architect
|
Schematic Design
|
Design Development
|
Construction Documents
|
Proposals
|
Construction
|
Closeout
|
|
Meadow Village ES - Addition
|
March 2009
- July 2010
|
||||||
|
John Glenn ES - Addition
|
February
2009 - July 2010
|
||||||
|
Marshall HS - Auditorium
|
February 2009
- July 2010
|
||||||
|
Ott ES - Addition
|
March 2009 - July 2010
|
||||||
|
Clark HS - Science
|
|
January 2009 - August 2010
|
|||||
|
Holmes HS - Science
|
February 2009 - August 2010
|
![]()
![]()
|