New Schools: (12)
Construction Cost: $323.5 Million
New Construction:
School Name |
Architect/Engineer |
Construction Budget |
Construction |
Opening |
Construction Completion |
|
|
($ Million) |
Award |
Date |
Date |
| Kuentz Elementary 1 - Leslie Road |
O'Neill, Conrad, Oppelt |
20.0 |
Oct-07 |
Aug-09 |
June-09 |
| Langley Elementary 2 - Steven Ranch |
Garza/Bomberger |
20.0 |
Jan-08 |
Aug-09 |
June-09 |
| Hoffmann Elementary 3 - Alamo Ranch |
PBK-Architects |
19.0 |
Sept-07 |
Aug-09 |
May-09 |
| Martin Elementary 4 - Canterbury Farm (660) |
Alamo |
18.0 |
Sept-08 |
Aug-10 |
May-10 |
| Behlau Elementary 5 - Laurel Mountain Ranch |
Noonan & Rittimann |
20.0 |
Oct-08 |
Aug-10 |
May-10 |
| Henderson Elementary 6 - Kallison Ranch #1 |
Marmon Mok |
20.0 |
Jan-09 |
Aug-10 |
May-10 |
| Elementary 7 - Bandera Rd. North |
O'Neill, Conrad, Oppelt |
21.0 |
Sept-09 |
Aug-11 |
N/A |
| Lieck Elementary 8 - Weston Oaks Area |
Noonan & Rittimann |
21.0 |
Oct-09 |
Aug-11 |
May-11 |
| Elementary 9 - Westwinds |
PBK-Architects |
20.0 |
Jan-10 |
Aug-11 |
May-11 |
| |
|
|
|
|
- |
| Hector Garcia Middle School 1 - Kyle Seale Pkwy Area |
Noonan & Rittimann |
39.0 |
Sept-07 |
Aug-09 |
June-09 |
| Briscoe Middle School 2 - Alamo Ranch |
PBK-Architects |
40.0 |
Aug-08 |
Aug-10 |
May-10 |
| Brennan High School - Potranco West Area |
Marmon Mok |
82.0 |
Dec-07 |
Aug-10 |
June-10 |
| |
|
|
|
|
|
School Additions: (9)
Construction Cost: $66.7 Million
Additions:
School Name |
Architect/Engineer |
Construction Budget |
Construction |
Opening |
Construction Completion |
|
|
($ Million) |
Award |
Date |
Date |
| Clark & Holmes - Science Labs (14ea.) |
Noonan & Rittimann |
24.0 |
Feb-09 |
Aug-10 |
Aug-10 |
| Jay High School (18ea.) |
Alamo |
13.9 |
Feb-08 |
Aug-09 |
Dec-09 |
| Taft High School (1ea.) |
|
1.2 |
Mar-08 |
Aug-09 |
N/A |
| Warren HS -Construction Trade |
Garza/Bomberger |
7.5 |
May-09 |
Aug-10 |
July-10 |
| Pease Middle School (17ea.) |
Garza Architects |
11.0 |
Mar-09 |
Aug-10 |
Aug-10 |
| Rayburn Middle School (17ea.) |
Garza/Bomberger |
12.6 |
Feb-08 |
Aug-09 |
Aug-09 |
| Adams Hill Elementary (15ea.) |
N/A |
7.5 |
Mar-10 |
Aug-11 |
N/A |
| Meadow Village Elementary (10ea.) |
West East Design Group |
4.5 |
Apr-09 |
Aug-10 |
Aug-10 |
| Ward Elementary (9ea.) |
Noonan & Rittimann |
3.1 |
Apr-09 |
Aug-09 |
June-09 |
| |
|
|
|
|
|
School Renovations: (5)
Construction Cost: $21.8 Million
Renovations:
School Name |
Architect/Engineer |
Construction Budget |
Construction |
Opening |
Construction Completion |
|
|
($ Million) |
Award |
Date |
Date |
| Marshall High School |
PBK-Architects |
8.0 |
|
Aug-10 |
Dec-10 |
| Neff Middle School - Library |
Pfluger + Architects |
1.8 |
|
Aug-09 |
Aug-09 |
| Cable Elementary - Library |
SHW |
1.0 |
|
Aug-09 |
June-09 |
| Glenn Elementary (Replacement) |
O'Neill, Conrad, Oppelt |
9.0 |
|
Aug-10 |
Aug-10 |
| Oak Hills Terrace Elementary - Library |
Pfluger + Architects |
3.5 |
|
Aug-10 |
Aug-10 |
| |
|
|
|
|
|
Kitchens: (4)
Construction Cost: $3.2 Million
School Name |
Architect/Engineer |
Construction Budget |
Construction |
Opening |
Construction Completion |
|
|
($ Million) |
Award |
Date |
Date |
| Sul Ross Middle School |
|
1.2 |
|
Aug-10 |
N/A |
| Zachry Middle School |
|
0.8 |
|
Aug-10 |
N/A |
| Howsman Middle School |
|
0.6 |
|
Aug-10 |
N/A |
| Villarreal Elementary |
|
0.6 |
|
Aug-10 |
N/A |
| - |
|
|
|
- |
- |
| |
|
|
|
|
|
Infrastructure:
Construction Cost: $43 Million
School Name |
Architect/Engineer |
Construction Budget |
Construction |
Opening |
Construction Completion |
|
|
($ Million) |
Award |
Date |
Date |
| HVAC |
Various |
22.0 |
|
Aug-10 |
- |
| Roofs |
Various |
12.0 |
|
Aug-10 |
- |
| Gym AC - Middle & High School |
Wallis Engineering |
9.0 |
|
Aug-09 |
- |
| - |
|
|
|
- |
- |
| - |
|
|
|
- |
- |
| |
|
|
|
|
|
|